FAQ's

Chrono & ChronoDASH Training Guide for New Users

Welcome to Chrono, a powerful tool by RTConfidence for managing project schedules and risks in the A&Dand Space industries. This guide introduces new users to Chrono’s core features: creating an Integrated Master Schedule (IMS), running Schedule Risk Analysis (SRA), and performing Earned Value Management (EVM). Follow these steps to get started and effectively manage your projects.

Getting Started with Chrono

Overview
Chrono helps you plan, track, and analyze project schedules with tools like wizards, automated metrics, and risk simulations. It’s designed to simplify complex project management tasks using a user-friendly interface.

Initial Setup

1.  Download and Open Chrono:

After downloading, locate the sample
file: Documents/RTConfidence/ChronoAdvTraining.mpt.
Save a copy with a new name (e.g., MyProject.mpt) to avoid overwriting the template.
Open the file in Chrono; it launches with the Chrono Tab active.

2. Log In:

When prompted, use the email address from your download and set a password.
This grants access to simulation outputs and cloud-based processing.

3. Understand the Chrono Tab:

The Chrono Tab is your main hub for most actions (e.g., running simulations, updating tasks).
Exception: Adjusting non-working days requires accessing the Project Calendar outsidethe Chrono Tab.

Building an Integrated Master Schedule (IMS)

What is an IMS?
An IMS is a comprehensive project schedule that outlinestasks, durations, dependencies, and resources. Chrono helps you create an IMSready for risk analysis and EVM.

Steps to Create an EVM-Ready IMS

1. Use the Reference Template

Start with ChronoAdvTraining.mpt, a pre-built IMS template.
Review tasks, durations, and dependencies in the Gantt chart view.

2. Set 3-Point Estimates for Risky Tasks:

Identify tasks withuncertainty (e.g., design, testing, or outsourced work).
Use the Chrono Wizard to input:
       Best-Case Duration: Optimistic estimate.
       Most-Likely Duration: Expected estimate.
       Worst-Case Duration: Pessimistic estimate.
Example: For a task with potential delays, input "Up to a 45 work-day slip due to more iterations than expected."

3. Define Task Relationships:

Set predecessors and successors to establish task dependencies.
Example: If Task ID 68 must finish before Task ID 69 starts, set Task ID 68 as the predecessor.

4. Validate the IMS:

Use Chrono’s validation tools to ensure no errors (e.g., missing dependencies or illogical durations).
Validation is critical for accurate SRA and EVM.

5. Add Cost Data:

Input resource costs (e.g., $57,600 for an Electrical Engineer for a task).
Assign resources via the Resources Tab in the task details.

Performing Schedule Risk Analysis (SRA)

What is an SRA?
SRA uses Monte Carlo simulations to predict schedule risksand estimate completion dates with confidence levels.

Running an SRA

1.  Prepare the IMS:

Ensure your IMS is validated and includes 3-point estimates for risky tasks.
Save your project file to preserve the baseline.

2.  Run the Simulation:

In the Chrono Tab, click Run Simulation.
Log in if prompted, then view the Browser Simulation Output (e.g., distribution charts, tornado charts).
Check the Commitment Milestone (the final IMS milestone) in the distribution chart.

3.  Interpret Results:

Distribution Chart: Shows the probability of meeting the project completion date.
Tornado Charts: Highlight tasks with the highest risk impact.
Gantt Charts: Display critical path and risk-adjusted schedules.
Example: A 73% commit confidence indicates a high likelihood of meeting the schedule.

4.  Update After Changes:

If you modify tasks (e.g., delete a successor like Task ID 123), re-run the simulation to update outputs.
Look for Red Flags in the interface, signaling that a simulation is needed.

Performing Earned Value Management (EVM)

What is an EVM?
EVM tracks project performance by comparing planned work(Planned Value), completed work (Earned Value), and actual costs.

Key EVM Metrics

Earned Value (EV): Value of completed work based on estimated costs.
Planned Value (PV): Budgeted cost of scheduled work.
Actual Cost (AC): Costs incurred for completed work.
Schedule Performance Index (SPI): SPI = EV / PV (measures schedule efficiency).
Planned Value (PV): Budgeted cost of scheduled work.
Cost Performance Index (CPI): CPI = EV / AC (measures cost efficiency).
Earned Schedule (ES): Alternative to SPI, based on task durations (ES = Baseline Duration * % Complete).


Steps to Perform EVM

1. Set Up EVM

Ensure your IMS has a baseline Budget at Completion (BAC).
Input actual costs for completed tasks via the Chrono Wizard.

2.  Track Progress:

Update task % Complete and actual costs periodically (e.g., during updates on 5/30/2025, 6/27/2025).
Example: For Task ID 68, add 5 days to remaining duration if delayed.

3. Review Metrics:

View EVM metrics (SPI, CPI, ES) in the Gantt view.
Use Distribution Trend Charts to monitor project health over time.

Updating and Re-Baselining the Schedule

Updating the Schedule

1.  Use the Project Progress Update Wizard:

Set the update date (e.g., 5/30/2025 for Update #1).
Record task progress (e.g., % Complete, days remaining).
Example: For Update #2 on 6/27/2025, adjust Task ID 68’s remaining duration from 9 to 14 days.

2. Preview and Publish

Select Preview to review changes in the Gantt chart.
Click Publish to finalize updates and update charts (e.g., SPI/CPI trends).


Re-Baselining the Schedule

1.  When to Re-Baseline:

Re-baseline if major changes occur (e.g., design changes requiring new tasks).
Example: Add a new “Schematic Design 2” task (Task ID 69) with a 30-day duration.

2.  Steps to Re-Baseline:

Save a new file version (e.g., MyProject_BL_and_Updates.mpt).
Make changes (e.g., adjust Task ID 70’s duration from 90 to 120 days).
Run a simulation to check the new commit confidence (e.g., from 0% to 73%).
Reset milestone dates to align with the updated schedule.

Key Tips for Success

Save Regularly: Always save a copy of your project file before major changes.
Run Simulations Often: Re-run simulations after any task or dependency changes to keep     outputs current.
Use Wizards: Chrono’s wizards simplify tasks like setting 3-point estimates and updating     progress.
Check DCMA 14-Point Metrics: Use Chrono’s automated evaluation to ensure your IMS meets     industry standards.
Understand Risks: Focus on high-risk tasks (e.g., design, testing, outsourcing) and     use SRA outputs to mitigate them.

Why Chrono?

Chrono, powered by RTC Monte Carlo X, offers:

Ease of Use: Intuitive wizards reduce training time.
Risk Insights: Monte Carlo simulations provide realistic risk assessments.
Data-Driven Decisions: Automated EVM and ES metrics support better project control.
Industry Compliance: Aligns with A&D standards like DCMA 14-Point Metrics.
Understand Risks: Focus on high-risk tasks (e.g., design, testing, outsourcing) and     use SRA outputs to mitigate them.

For more information, visit RTConfidence.com.

Introduction to Chrono and ChronoDASH

Chrono is an AI-ML- enabled SaaS solution for project portfolio management, schedule risk analysis, and earned value management. It is designed to help teams proactively manage risks, meet deadlines, and control costs with minimal training.

ChronoDASH is a browser-based dashboard that allows users and reviewers to view project outputs, such as Gantt charts and simulation results, without needing a Microsoft Project license.

Key Features and Benefits

Chrono Core Features

Integrated Master Schedule (IMS) Tools
Schedule Design Wizard
Auto-validation and auto-baseline
Target and commitment schedules
Schedule Risk Analysis (SRA)
Simulation setup wizard
Early warning indicators
Fast simulation speed
Earned Schedule & Value Management
Project update wizard
Probabilistic cost analysis
Early warning indicators

ChronoDASH Features

View all output graphics via browser
No MS Project license required for reviewers
Easy sharing of Gantt charts and simulation results

Benefits for Users

Saves time on project management tasks
Automates risk-adjusted roll-ups for large schedules
Minimal training required due to expert system wizards
Early warning KPIs for schedule and cost risks
Helps teams define, track, and mitigate project risks

How Chrono Works: Step-by-Step

A.  Project Setup

1.  Start a New Project

Use the Blank Project Start-up Wizard or import an existing project file.

2.  Design the Schedule

Use the Gantt Chart Setup Wizard to create or refine your project schedule.

3.  Validate the IMS

Run the IMS Validation Wizard to check for logic errors, missing links, and other issues.


B.  Risk Analysis and Baselines

4.  Run Schedule Risk Analysis

Use the RTC Monte Carlo X Simulation Wizard to assess schedule risks and generate probabilistic forecasts.

5.  Set Baselines

Establish project baselines using the Project Baselines Wizard.


C.  Project Execution and Monitoring

6.  Update Progress

Use the Project Progress Update Wizard to record actuals and update forecasts.

7.  Re-baseline as Needed

If significant changes occur, use the Re-Baselining Wizard.

8.   Monitor KPIs

Track key performance indicators (SPI, CPI, % confidence, trend data) for early warnings.


D.  Review and Reporting

9.  Share Results

Use ChronoDASH/ChronoView to share Gantt charts and simulation outputs with stakeholders.

10.  Continuous Improvement

Use trend data and KPIs to identify issues early and adjust plans proactively.

Best Practices for New Users

Leverage Wizards: Use the built-in wizards for every major step—setup, validation, simulation, updates, and reporting.
Validate Schedules: Always run the IMS Validation Wizard before setting baselines.
Use Probabilistic Estimates: Enter realistic, risk-adjusted task durations rather than single-point estimates.
Monitor KPIs Regularly: Check the dashboard for early warning signs and act promptly.
Share Outputs: Use ChronoDASH to keep all stakeholders informed without extra software.

Quick Reference Table: Chrono Wizards

Seamlessly integrates Schedule Risk Analysis (SRA), Earned Value Management (EVM), and Cost Risk Analysis (CRA) to proactively identify and mitigate risks, enhancing project resilience.

Wizard Name

Blank Project Start-up
Project File Import
Gantt Chart Setup
IMS Validation
RTC Monte Carlo X  Simulation
Project Baselines
Project Progress  Update
Re-Baselining
SRA Output
ES (Earned Schedule) Output
Merge Bias
IMS Roll-ups
ChronoDASH

Purpose

Create a new project from scratch
Import existing schedules
Build or edit project schedule
Check for schedule logic errors
Run risk analysis simulations
Set official project baselines
Record actual progress
Adjust baselines after major changes
Generate risk analysis reports
Track earned value metrics
Analyze schedule merge bias
Aggregate schedules for large projects
Share outputs with stakeholders

When to Use

Project initiation
Project initiation
Planning
Before baselining
After planning
After validation
During execution
As needed
After simulation
During execution
After simulation
For large/complex projects
Reporting

Tips for Success

Start simple: Use the wizards to guide you through each step.
Iterate: Update and re-baseline as your project evolves.
Communicate: Use ChronoDASH to keep everyone aligned.
Act on KPIs: Don’t ignore early warnings—address issues promptly.

General Product FAQs

What is RTConfidence, and what solutions do you offer?

RTConfidence provides advanced Project Portfolio Management (PPM) tools designed to help organizations improve delivery outcomes, manage risk, and enhance visibility across projects. Our solutions include Chrono, ChronoDASH, and AgileDASH, — each tailored to different aspects of scheduling, risk analytics, and portfolio oversight.

What makes ChronoDASH different from other PPM tools?

ChronoDASH uniquely combines risk-based analytics, real-time visibility, and low-codecustomization into a single dashboard. It’s built to identify schedule and costrisks early, support executive reporting on demand, and enable organizations tomanage portfolios with clarity and confidence.

Is RTConfidence software cloud-based or on-premises?

RTConfidence solutions are cloud-based SaaS platforms,offering secure, scalable access from anywhere. On-premises options may beavailable upon request for specific enterprise needs.

Do your tools integrate with Microsoft Project, Primavera (P6), or other scheduling tools?

Yes. Our tools integrateseamlessly with Microsoft Project, Oracle Primavera P6, and otherindustry-standard IMS (Integrated Master Schedule) tools, allowing you to workwithin your preferred scheduling environment.

What industries benefit most from RTConfidence solutions?

Our solutions are ideal forindustries with complex project portfolios and strict delivery requirements,such as aerospace and defense, energy, construction, government, andlarge-scale manufacturing.

Capabilities & Features

What is Risk-Adjusted Scheduling (RAS), and how does it work?

Risk-Adjusted Scheduling(RAS) integrates probability-based analysis into your project schedules,enabling early identification of vulnerabilities and data-driven scenarioplanning. This capability enhances schedule reliability and provides leaderswith actionable insights for proactive decision-making.

How does ChronoDASH support Earned Value Management (EVM)?

ChronoDASH automates Earned Value Management by embedding cost, schedule, and performancemetrics directly into the project dashboard. It provides executives with areal-time view of cost efficiency and project progress, helping organizationsmaintain control over both scope and budget.

Can I create and manage sub-portfolios and master schedules?

Yes. RTConfidence solutionsoffer full support for complex portfolio hierarchies, allowing teams to managesub-portfolios and roll them into master schedules. This provides programleaders and PMOs with a consolidated, risk-aware view of enterprise-wideperformance.

Does your platform provide Schedule Risk Assessment (SRA) and Cost Risk Assessment (CRA)?

Absolutely. Our toolsintegrate Monte Carlo simulation and other proven methodologies to conductrobust Schedule and Cost Risk Assessments. These insights support projectsteering decisions and enhance the organization’s ability to meet deliverycommitments.

How does RTConfidence support agile and hybrid project environments?

With our Risk-AdjustedAgile Framework (RAAF), RTConfidence enables teams to apply risk-based thinkingto agile execution. This hybrid capability allows organizations to maintainagility while managing portfolio-level risk, compliance, and scheduleintegrity.

Analytics & Reporting

What types of reports and dashboards are available?

RTConfidence provides a suite of dynamic, interactivedashboards and automated reports designed for both project teams and executivestakeholders. These include performance trends, earned value metrics, schedulevariance, risk exposure, and predictive forecasts — all accessible inreal-time.

Is real-time portfolio health reporting included?

Yes. ChronoDASH delivers real-time visibilityinto the health of individual projects and entire portfolios. Key indicatorsare automatically updated based on actual schedule and cost performance,enabling timely, informed oversight at every level.

How does the platform automate executive-level reporting?

Our platform eliminates the need for manual dataconsolidation by automatically generating executive-ready reports. Thesereports synthesize cost, schedule, and risk data into concise, visuallycompelling summaries tailored for strategic decision-makers.

Security & Access Control

What kind of data security measures are in place?

RTConfidence solutions arebuilt on secure, cloud-based architecture with enterprise-grade encryption,secure user authentication, and data integrity controls. We follow industrybest practices to protect sensitive project data and ensure compliance with ITgovernance standards.

Can I control access and permissions by role or project?

Yes. Our platform featuresrobust role-based access controls (RBAC), allowing you to define userpermissions at the portfolio, program, or project level. This ensures thatstakeholders see only what’s relevant to them, while maintaining centralizedoversight.

How does RTConfidence handle sensitive project and cost data?

We treat project and costdata with the highest degree of confidentiality. Data is encrypted in transitand at rest, and access is tightly managed through configurable permissions.This ensures secure collaboration across teams and departments without compromisingcompliance or control.

Integration & Customization

Does RTConfidence integrate with my existing PMO tools?

Yes. RTConfidence seamlessly integrates with leadingproject management tools such as Microsoft Project, Oracle Primavera P6, andothers. This ensures continuity across your current workflows while enhancingyour capabilities with advanced risk and portfolio intelligence.

Can the software be customized to fit my organization’s governance model?

Absolutely. Our platform isdesigned with flexibility in mind. You can tailor workflows, dashboards, KPIs,and reporting structures to align with your organization's governancestandards, compliance needs, and management methodologies.

Is it compatible with our internal data visualization tools (e.g., Power BI)?

Yes. RTConfidence supportsAPI access and data exports that allow integration with tools like Power BI andTableau. This enables your analytics teams to incorporate PPM insights intobroader enterprise intelligence environments.

Implementation & Support

What does the implementation process look like?

Our implementation approachis streamlined, collaborative, and scalable. We begin with a discovery phase toalign with your organizational needs, followed by configuration, integration,and training. Most clients are up and running within weeks, with minimaldisruption to existing operations.

Is there training available for my team?

Yes. RTConfidence offers comprehensive training for usersat all levels — from project managers to executives. This includes liveworkshops, documentation, and ongoing support to ensure rapid adoption andlong-term success.

What kind of customer support do you provide?

We provide responsive,expert-led customer support, including onboarding assistance, technicaltroubleshooting, and best-practice guidance. Dedicated support packages areavailable for enterprise clients to ensure continued alignment with yourevolving portfolio needs.

Pricing & Licensing

What is the pricing model for RTConfidence tools?

RTConfidence offers flexible pricing based onorganizational size, number of users, and solution scope. We provide bothsubscription-based and enterprise licensing options to support scalability andbudget alignment.

Are there different tiers or packages?

Yes. We offer modular packages that allow you to start withcore capabilities and expand as your needs grow. Solutions can be tailoredaround specific functions — such as schedule risk analysis, earned valuemanagement, or enterprise reporting — ensuring you only pay for what you need.

Do you offer a free trial or demo version?

We offer personalized demos and limited pilot engagements to help your team evaluate the platform in areal-world context. These sessions are designed to showcase value, assess fit,and align the solution with your strategic objectives.

Still have question?

Request Info

Request A Demo